Van Stee Offshore is proud to announce the successful installation of the third and final crane on its shallow draughted flagship ”Zwerver V”. The vessel returned to the Netherlands in January 2025 for the integration of this final piece of heavy equipment at the port of Vlissingen.
The crane installation marks the completion of the Zwerver V’s outfitting program. The new crane is an active-heave compensated offshore knuckle boom crane fabricated by Scaldon and with a lifting capacity of 100 tonnes, adding enhanced versatility and lifting power to the vessel’s already extensive capabilities. This setup allows “Zwerver V” to perform a wide range of offshore support activities, including subsea operations, heavy cargo handling, and precision lifting tasks in challenging marine environments.
Our DP2 “Zwerver II” has completed her operations in Taiwanese waters in October 2024.
The vessel was involved in the installation of the Yunlin OWF which is located in shallow waters at the W-Coast of Taiwan, and spend 4 seasons in a row to support a variety of operations.
Her main scope of work was anchor-handling operations with the installation vessels and barge support operations.
From February 2023 till September 2024, the “Zwerver III” was involved in a large dredging project in Sokhna (Egypt).
The vessel supported various dredging vessels and equipment during this period.
Our DP2 “Zwerver I” is working on a longterm charter as DSV. The project is in shallow waters and vessel operates on 4-point mooring and in DP2.
The versatile vessel employs all of its capabilities on this project and serves as the ultimate support vessel.
The scope of work consists of diving operations, anchorhandling, SPM buoy maintenance and survey operations.
The DP-2 “Zwerver II” conducted in October/November 2019 another scope of remedial works on IFA2 Interconnector.
On deck of the vessel, our charterer mobilized a serious massflow spread (more…)